Subcontractor resource has zero rate

My Subcontractor resource isn't showing a value The Rate on the Subcontractor I just added is 0, shouldn't it be 1?

Written by Andrei Ene

The rate on a subcontractor, except in exceptional circumstances should always be 1. However, sometimes these resources are entered into the library incorrectly and we have occasionally seen Cloned resources not pull the Rate across.
​
To correct this on an individual project:

  1. Go to Analysis, Estimating, Job Resources

  2. Find the problem resource

  3. Check Allow Changes

  4. Change the Rate to 1 and if required, add the Unit (£)

If you are the library manager and are correcting this in the library:

  1. Go to Library, Resources, Amend Resources

  2. Find the problem Resource

  3. Check Allow Changes

  4. Change the Rate to 1 and if required, add the Unit (£)