The Gross resource rate in Comparisons is different from that shown in the Estimate.
Run the Tools, Check Job, Preview, OK function
Run Trade, Update function from Comparisons to update the project
If the update function is ran with attendances, adjustments, and discounts applied and changes are made to the Estimate regarding Qty's the update function will need to be reapplied to the trades changed. The Update Multiple Trades function can be used to update multiple rates for multiple trades at the same time rather than trade by trade.
Tools
Select Comparisons
Then Update Multiple Trades.